Production Summary July 10, 2026

Status

The first 500 units are anchored to an October 16 delivery from Eastek.

Timeline

2026 → 27
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Decide
Eastek call Jul 13
Tooling
Tool correction check
Mold run
If stock short - book by mid-Aug
Parts
Short-part buys + PCBA completion (80 of 500)
Battery
Pytes EOL → BFN swap
Packaging
Artwork sent Jul 8 → print + boxes
Assembly
Assembly + QA + fit
Ship
Dock - Oct 16
Next run
Second 500 - Jan 1
Active workstream Build + delivery Only if stock falls short ★ = decision point / dock date

Key issues

1. Housing fit - assembly vs mold
Mark’s July 6 read is that the top-bottom mismatch is parts variation and tolerances, hard to judge from a single sample.
2. Inventory reconciliation
The stock count needs squaring before we size any mold run.
3. Battery end-of-life
The Pytes cell is discontinued; Eastek proposes the BFN alternate at the same specs and cost.
4. Packaging release
The full artwork, manual, and drawings pack went to Eastek July 8.
5. PO size (EAU)
Keith’s open question is whether the 25K blanket PO is still right.

Next steps

Monday, July 13 - Eastek status call
Mark / SmartShape
Hold October 16
Full production tracker: lumimed.novopartners.com  ·  Prepared July 10, 2026 · Novo Partners