Eastek call handouts, August 11, 2026
Open items checklist — 16 items with date first asked and days outstanding.
Parts shortage list — 34 short line items off Eastek's June 9 report (Excel).

Production Summary July 15, 2026

July 13 follow-ups

The build is not ready to commit: Eastek still owes real dates, the housing path is not settled, and the 25,000-unit document is not a valid signed contract.

Timeline

2026 → 27
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Contract
Review 25K order + economics
Tooling
Tool correction check
Fit test
Stock-parts evaluation
Parts
Parts + PCBA dates pending
Battery
Pytes EOL → BFN review
Packaging
Files sent Jul 8 → print hold
Assembly
Assembly + QA + fit
Ship
Requested - Oct 16
Next run
Requested - Jan 1
Active workstream Build + requested delivery Decision follows stock-parts evidence ★ = checkpoint / requested delivery

Key issues

1. Contract and economics
The 25,000-unit document is not a valid signed contract, so it does not set today's quantity or price.
2. Production dates
Eastek still has not given us a reliable stock count, quote, or dock dates.
3. Product readiness
The housing, replacement battery, and FDA pre-submission still need clear answers.
Full production tracker: lumimed.novopartners.com/tracker  ·  Updated July 15, 2026 · Novo Partners