Production Summary July 15, 2026
July 13 follow-ups
The build is not ready to commit: Eastek still owes real dates, the housing path is not settled, and the 25,000-unit document is not a valid signed contract.
- Contract and economics: review the 25,000-unit order and old pricing before anyone signs or commits. The document has been reviewed and revised, but it is not a valid contract; settling the terms is a priority over the next few weeks.
- Production: get Eastek's real stock count, quote, and dock dates for the first 500 units.
- Product readiness: verify the housing fix, decide stock parts versus mold work, and close the FDA and battery questions.
Timeline
2026 → 27
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Contract
Review 25K order + economics
Tooling
Tool correction check
Fit test
Stock-parts evaluation
Parts
Parts + PCBA dates pending
Battery
Pytes EOL → BFN review
Packaging
Files sent Jul 8 → print hold
Assembly
Assembly + QA + fit
Ship
Requested - Oct 16 ★
Next run
Requested - Jan 1
Active workstream
Build + requested delivery
Decision follows stock-parts evidence
★ = checkpoint / requested delivery
Key issues
1. Contract and economics
The 25,000-unit document is not a valid signed contract, so it does not set today's quantity or price.
- Review the order, invoices, pricing, and release terms before anyone signs or commits.
2. Production dates
Eastek still has not given us a reliable stock count, quote, or dock dates.
- Get written dates for the October 16 and January 1 requests.
3. Product readiness
The housing, replacement battery, and FDA pre-submission still need clear answers.
- Verify the tool fix, test stock parts, and close the NAMSA and battery review.