Eastek Parts Shortage: Lumimed 500-Unit Build

Companion to the open-items sheet. For the Eastek call, Tuesday August 11, 2026, 2:00 PM ET.
Eastek's own shortage report, dated June 9, 2026, lists 34 short line items against the 500-unit build. Sixty-three days later not one has a committed dock date. Quoted lead times run from 15 days to 378 days, so the longest of these decides October 16, and nothing on this sheet has been re-quoted since.

How to read this

Short line items

#PartDescriptionShortLead (d)On order First reportedDays outCommitted dock date
Electronics
1CAP0041Capacitor 2200pF 50V X7R5003780Jun 9, 202663
2DIO0011Diode TVS unidirectional 6V273570Jun 9, 202663
3MHW0009Battery holder743400Jun 9, 202663
4DIO0010Diode Schottky power583250Jun 9, 202663
5WIR0010Red 22AWG hookup wire8231680Jun 9, 202663
6WIR0011Black 22AWG hookup wire8241680Jun 9, 202663
7CAP0045Capacitor ceramic 4700pF14215069Jun 9, 202663
8BAT0002Battery lithium manganese5001100Jun 9, 202663
9WIR0009Black 24AWG wire14571050Jun 9, 202663
10CON0007Connector FFC 4-pos 1mm4321050Jun 9, 202663
11CAP0047Capacitor ceramic 50V 2.2uF79910Jun 9, 202663
12RES0066Resistor 1/2W 1.5 ohm57900Jun 9, 202663
13CAP0043Cap ceramic 50V NP0 040284800Jun 9, 202663
14RES0052Thermistor NTC 100K127700Jun 9, 202663
15OSC0003Buzzer 2700Hz 3V31650Jun 9, 202663
16CHM0001Indium solder 8.9HF(T5)350450Jun 9, 202663
17LED0002LED green SMT 0805408400Jun 9, 202663
18CHM0002Solder wire Telecore HF-8501350Jun 9, 202663
19PCBA0008-1Main board SMT (80 of 500 built)42000Jun 9, 202663
Molded & mechanical
20COV0009Polyurethane rubber bumper111191200Jun 9, 202663
21LPL0007Light pipe (molded)12990Jun 9, 202663
22COV0013Ring adhesive 3M 9059MP16990Jun 9, 202663
23IMM0055Cone cap (molded - Lumimed tooling)500840Jun 9, 202663
24MHW0075Heatsink (molded)425840Jun 9, 202663
25IMM0048Cover cap (molded)5840Jun 9, 202663
26IMM0056Charger base bottom (molded)6840Jun 9, 202663
27IMM0057Charger base (molded)6840Jun 9, 202663
Packaging & printed
28LBL0009Charger information label1000990Jun 9, 202663
29INS0004Owners manual500400Jun 9, 202663
30BOX0109Top/bottom set-up box500300Jun 9, 202663
31BOX0110Corrugate DW pad1000300Jun 9, 202663
32BOX0111Corrugate insert1000300Jun 9, 202663
33BOX0112Set-up box 24-pk shipper21300Jun 9, 202663
34LBL0053Label blank 2x3.5 polyester500150Jun 9, 202663

The three that decide the date

The question to put on the table

Anthony's framing from August 7: Eastek claims 415 units are completable, so we need 85 more. Which of these line items are short for the last 85, in what quantity, and what date is committed for each. That is a one-page answer off their own report and it has been outstanding since June 9.