Eastek Open Items: Lumimed 500-Unit Build

Prepared for the Eastek call, Tuesday August 11, 2026, 2:00 PM ET. Dates below are the date each item was first asked for, on the record.
Eastek holds components for roughly 412 to 418 of the 500 units and is short about a dozen electronics parts, and no part-numbered shortage list with committed dates has ever been produced. The oldest open ask on this sheet dates to June 25. Everything on the October 16 delivery date rests on the last 85 units.

The agenda: five things to get out of this call

  1. Lock the shortage list. Which parts are short for the last 85 units, in what quantity, with a committed date on each.
  2. Confirm or lose October 16. A yes or no on the date, said out loud, with the parts answer behind it.
  3. Communicate that we stage orders. First build 500, then 2,000 to 5,000. No answer on the 25,000 number today.
  4. Get the root cause in writing. Eastek and SmartShape jointly on the housing misalignment, before any release of the balance.
  5. Confirm the drawing revision and the delivery dates. Which revision they build to, and when the pilot and pre-production units shipped.

Summary notes, prior meetings

Open items checklist

Days outstanding are counted to today, August 11, 2026. The last column is deliberately blank, to be filled in live on the call.

# Item we have been asking for Date first asked Days out Today Eastek response / committed date
1Shortage list by part number for the remaining 85 units, with committed dates for eachJun 25, 202647Aug 11, 2026
2Adjusted quote for the 500-unit build with written lead times (Scott Roberts)Jun 25, 202647Aug 11, 2026
3Exact count of components on hand, confirming the 412 to 418 figureJun 25, 202647Aug 11, 2026
4Confirmation the October 16 delivery date for the first 500 still holds, and January 1 for the second 500Jun 10, 202662Aug 11, 2026
5Status of the SmartShape components shipped to Eastek in 2022: located, counted, usableJul 9, 202633Aug 11, 2026
6Whether Eastek is re-ordering plastic parts already on hand, and at whose costJul 10, 202632Aug 11, 2026
7Written joint root cause on the two-shot lower-enclosure misalignment, with Eastek and SmartShape both on itJul 13, 202629Aug 11, 2026
8Delivery dates for the 10 black pilot units and the 4 white pre-production unitsJul 24, 202618Aug 11, 2026
9Authorization to release 20 to 50 units off the corrected process for physical inspection before the balanceJul 24, 202618Aug 11, 2026
10Which drawing revision Eastek is building to, reconciled against Lumimed's current revisionJul 31, 202611Aug 11, 2026
11Tooling material confirmation, aluminum or steel, in writingJul 24, 202618Aug 11, 2026
12Pytes battery end-of-life: last-time-buy terms, the BFN alternate, and whether a swap triggers revalidationJul 8, 202634Aug 11, 2026
13Assembly and glue solution for the lip issue, and whether Eastek is fixing the core problem insteadJul 28, 202614Aug 11, 2026
14Confirmation of what packaging documentation is still outstanding on Lumimed's side: giftbox artwork, IFU manual, updated drawingsJun 25, 202647Aug 11, 2026
15Lead time for subsequent orders now that the first build is in processAug 7, 20264Aug 11, 2026
16Executed December 12, 2022 manufacturing and supply agreement with all schedules (Avery holds; Eastek can also produce)Jul 23, 202619Aug 11, 2026